Starting the year 2000, IECCA starts its construction activities, participating in several construction projects, among which we can mention the followings:
PROJECT DATA DESCRIPTION
Ecologic Avenue Construction
CLIENT:
AYUNTAMIENTO SANTO DOMINGO ESTE (ASDE)

DATE:
Junio 2008- marzo de 2010
Construction of boardwalks on the north and south side. Construction of a leisure park with social areas, children playground, parking lots, ilumination and gardening. Also a Gazebo and Water system where constructed.

Pedro Domínguez Garabito
School
School Construction
CLIENT:
SECRETARÍA DE ESTADO DE EDUCACIÓN

DATE:
2004-2008
Construction of the Pedro  Domínguez Garabito School in Cambita Garabito. The Esperanza Milena School was rehabilitated and expanded inLa Canela, Santiago.

The Manuel A. Machado School in Dajabón was rehabilitated and expanded. The Anacaona Almonte School in Santiago was repaired and expanded.  The Ansonia School in La Plena, Azua and the San José School in Vicente Noble were repaired as well.

The María Nicolasa Billini School in Los Llanos, San Pedro de Macorís was reconstructed and expanded. All of this constructions where constructed by the SEE termination statndars.}

Extensión of the National Judiciary School

CLIENT:
Escuela Nacional de la Judicatura (National Judiciary School)

DATE:
Abril/05-Noviembre/06

Construction of four (4) new classrooms, in steel structure, and rehabilitation of three (3) existent ones. Construction of rest rooms and other external facilities to connect the classrooms
 
Reinforcing and restructuring of the Duarte Bridge in Santo Domingo.

Duarte Bridge
CLIENT:
Secretaría de Estado
de Obras Públicas
 

DATE:
2005-2006

Project that includes the reinforcement of this 50 year old steel structure, reconstruction of the suspended cable system, application of a modern corrosion protection system, new lighting, side protection, repaving of the deck and pluvial drainage.
 
Civil Work for the 69/12.5 KV Substation in Rafey

Substation 69/12.5Kv

CLIENT:
ABB AS, Power Technologies Division.

DATE:
2005-2006

 

Civil works construction of the 69/1.5KV electrical substation located within the waste water treatment plant in Rafey.
 
Civil Works for the Extension and Rehabilitation of the Potable and Waste Water Treatment Plants of Coraasan, in Santiago de los Caballeros


Secondary Water Tratment 
Planta Rafey


Water Treatment Plant de La Noriega.

CLIENT:
Per Aarsleff A/S
 

DATE:
2004-2006

 

Civil Works for the construction of the extension in 1m3/sec of the Noriega potable water treatment, extension and rehabilitation of the waste water treatment plants of Rafey in 1m3/sec, Cienfuegos of 250 lps and Tamboril of 350 lps, construction of 6 new pump stations, within the contract signed between Denmark’s Per Aarsleff and la Corporación de Acueducto y Alcantarillado de Santiago

 
Rehabilitation of the aqueducts affected by Hurricane George’s (Villarpando) in the province of San Juan de la Maguana

 

 
CLIENT:
Instituto Nacional de Aguas Potables y Alcantarillados (INAPA)

DATE:
2000-2003

Construction of a 22 lps slow filtration water treatment plant, a 400 m3 reinforced concrete regulating reservoir, river bed intake, pumping house, 8" PVC main line of Villarpando aqueduct, within the rehabilitation program within Lote III of the International Development Bank (IDB) Loan 1152/OC-DR.
 
Rehabilitation of the aqueducts affected by Hurricane George’s (Las Lomas) in the province of Azua
  CLIENT:
Instituto Nacional de Aguas Potables y Alcantarillados (INAPA)

DATE:
2000-2003

Construction of a dike, a river bed filter and a 12" steel pipe line in the Las Lomas acueduct, within the rehabilitation program (Lote III) of the International Development Bank (IDB) Loan 1152/OC-DR.
 
Rehabilitation of the aqueducts affected by Hurricane George’s (Río Vía) in the province of Azua
  CLIENT:
Instituto Nacional de Aguas Potables y Alcantarillados (INAPA)

DATE:
2000-2003

Reconstruction of a 12" steel pipe line, rehabilitation of a dike, sand traps and a fast filtration water treatment plant (2 filters and 1 flocculation) in Río Vía acueduct within the rehabilitation program (Lote III) of the International Development Bank (IDB) Loan 1152/OC-DR.
 
Arroyo Blanco - El Guanal Multipurpose Aqueduct
  CLIENT:
Instituto Nacional de Aguas Potables y Alcantarillados (INAPA)

DATE:
1999-2003

Completion of a 11 lps slow filtration water treatment plant, main and discharge pipe lines, intake pumping house, distribution lines and reinforced concrete regulating reservoir.

OUR COMPANY EXPERIENCE ASSOCIATES CONTACTS
ABOUT US + SUPERVISION
+
DESIGN
+
CONSTRUCTION
+
FINANCING
 ASSOCIATES Tel.: (809) 541-6330
Fax : (809) 541-0089

 E-mail:
info@iecca.net
IECCA, S.R.L., All rights reserved